Unsteady flow in the 5 km intermediate canal between the M-3-1 and M-3-2 pumping stations during unit start-ups and shutdowns is modelled with the Saint-Venant equations. For depths of 2.0-3.0 m and roughness of 0.025-0.035, the optimal delay for starting a unit at M-3-2 after a start at M-3-1 is 17-58 min; it can be calculated within 5 % from the volume between two steady water surface profiles. Simultaneous start-up lowers the M-3-2 forebay level by 0.15-0.51 m.